- Duration: Flexible
Course details
- Most Repetitive 500 Questions on the Project Management Professional (PMP) Exams
- All Questions have Answers with Detailed Explanations
- Situation Based Questions ·
-------------------------------------------------------------------------------------------------------------------------------
- 5 Knowledge area specific questions
- Practice Test 6- HUMAN RESOURCE MANAGEMENTT : 100 QUESTIONS
- Practice Test 7-RISK MANAGEMENT : 100 QUESTIONS
- Practice Test 8-PROCUREMENT MANAGEMENT : 100 QUESTIONS
- Practice Test 9-STAKEHOLDER MANAGEMENT : 100 QUESTIONS
- Practice Test 10-COMMUNICATION MANAGEMENT : 100 QUESTIONS
------------------------------------------------------------------------------------------------------------------------------------
Sample Question:
1: The difference between a configuration management system and a change control system is?
a. The configuration management system is part of the PMIS - the change control system is not
b. The change control system is part of the key PMIS - the configuration management system is not
c. The change control system feeds into the configuration management system and is part of the configuration management system
d. Both the change control system and a configuration management system are organizational process assets
Answer : C
Explanation:
A and B are deliberate misdirection. D is incorrect. The change management system is subsumed within the configuration management system.
------------------------------------------------------------------------------------------------------------------------------------
Updated on 27 May, 2018- USD 13Duration: Upto 2 Hours
- Diploma for Project Manager Course LineUSD 24
USD 440Duration: Upto 5 Hours