  • Exam Title: Primavera P6 Enterprise Project Portfolio Management 8 Essentials
  • Most Repetitive 100 Questions on the Primavera P6 Enterprise Project Portfolio Management [EPPM]  Exam. 
  • All Questions have Answers with Detailed Explanations 
  • 100 % Passing Guarantee, once you Complete all the Practice Questions and Explanations.

--------------------------------------------------------------------------------------------------------------

Sample Question:

You are a portfolio manager, and a filter has been set to identity and assign projects to your portfolio. You are in Primavera P6 EPPM web interface. How could you be certain that the list of projects in your portfolio is complete?

A. By manually hiding projects

B. By manually adding new projects

C. By manually refreshing the filter

D. By manually updating projects

 Answer: C

Explanation: The result of filter can be refreshed to ensure that the most current information is displayed.

----------------------------------------------------------------------------------------------------------------